Pittsfield Street Improvement Project Schedule: Oct. 18-22| 04:48PM / Friday, October 15, 2021 | |
PITTSFIELD, Mass. — Please note the following work is scheduled for Oct. 18-22, as part of the City of Pittsfield’s 2021 Street Improvement Project.
The schedule is as follows:
-
Monday, Oct. 18: Pave speed tables on Velma Avenue and raise structures on Anita Drive.
-
Tuesday, Oct. 19: Pave Gordon, Deming, and High streets and raise structures on Curtain and Paul avenues, Maloney and Lucille streets.
-
Wednesday, Oct. 20: Pave Andover and Plumb streets, raise structures on Curtain and Paul avenues, Maloney and Lucille streets.
-
Thursday, Oct. 21: Pave Anita Drive, Hawthorne Avenue, and raise structures on Curtain and Paul avenues, Maloney and Lucille streets.
-
Friday, Oct. 22: Pave Oxford Street, Brenton Terrace, Cadwell Road, and raise structures on Hawk and Yarmouth streets, Cliff Avenue.
On-street parking is prohibited during this work between the hours of 6 a.m. and 6 p.m. each day.
The schedule is subject to change based on weather conditions.
|