PITTSFIELD, Mass. — The following road work is planned to take place starting Monday, Aug. 14:
-
Monday, Aug. 14: Paving Quirico Drive, Lucia Drive, Almar Drive
-
Tuesday, Aug. 15: Paving Brookside Drive & Ann Drive
-
Wednesday, Aug. 16: Curbing install Cloverdale Street
-
Thursday, Aug. 17 & Friday, Aug. 18: Milling California Avenue, Maryland Avenue, Allendale Road & Lakeway Drive. Curbing will be installed on Brookside Drive.
In addition, between Aug. 14-18, structures will be raised on Tamarack Road, Cloverdale Street, Quirico Drive and Lucia Drive.
This work will occur between the hours of 7 a.m. and 5 p.m. and is subject to change based on weather or other unexpected circumstances.
On-street parking is prohibited between the hours of 6 a.m.- 6 p.m.