Pittsfield Street Improvement Project: Aug 2 - 501:19PM / Thursday, August 01, 2024 | |
PITTSFIELD, Mass. — The city's street improvement work continues with the following schedule in place for August 2-5:
-
August 2: Milling of Harding Street and Kensington Avenue
-
August 5: Paving of Harding Street and Kensington Avenue and the removal of concrete on Dwight Street
On-street parking is prohibited during this work between the hours of 6 a.m. to 6 p.m.