May 27-28:
  • Loam and seed Backman Avenue, Daniels Avenue and Jason Street
May 27-30:
  • Raising structures on Newell Street
May 29-30:
  • Final course of paving on Orlando Avenue, Ridge Avenue, Backman Avenue and Jason Street
On-street parking, for the above streets, is prohibited during this work between the hours of 6 a.m.- 6 p.m.
 
In addition, MassDOT will be conducting the following work:
  • Adjusting structures and fixing curbing on North Street from Lanesborough town line to Berkshire Medical Center entrance (5/27-5/30)
  • Traffic loops at various intersections on First Street (5/27-5/29)
  • Traffic loops on South Street (5/30)
This schedule is subject to change based upon weather conditions.
 
More Featured Stories
Pittsfield.com is owned and operated by: Boxcar Media 106 Main Sreet, P.O. Box 1787 North Adams, MA 01247 -- T. 413-663-3384
© 2008 Boxcar Media LLC - All rights reserved