Pittsfield Street Improvement Project: May 27 to May 3004:12PM / Friday, May 23, 2025 | |
PITTSFIELD, Mass. — The following street improvements are scheduled from May 27 to May 30:
May 27-28:
-
Loam and seed Backman Avenue, Daniels Avenue and Jason Street
May 27-30:
-
Raising structures on Newell Street
May 29-30:
-
Final course of paving on Orlando Avenue, Ridge Avenue, Backman Avenue and Jason Street
On-street parking, for the above streets, is prohibited during this work between the hours of 6 a.m.- 6 p.m.
In addition, MassDOT will be conducting the following work:
-
Adjusting structures and fixing curbing on North Street from Lanesborough town line to Berkshire Medical Center entrance (5/27-5/30)
-
Traffic loops at various intersections on First Street (5/27-5/29)
-
Traffic loops on South Street (5/30)
This schedule is subject to change based upon weather conditions.
|