Pittsfield Street Improvement Project: June 2 to June 610:44AM / Monday, June 02, 2025 | |
PITTSFIELD, Mass. – The following street improvements are scheduled from June 2 to June 6:
-
June 2: Loam and seed on Newell Street
-
June 3: Final paving course Daniels Avenue
-
June 4: Final paving on Joseph Drive
-
June 5 & 6: Finish loam and seed and raising of structures on Newell Street and Meadow Lane
On-street parking, for the above streets, is prohibited during this work between the hours of 6 a.m.- 6 p.m.
In addition, MassDOT will be conducting the following work:
-
Adjusting structures and fixing curbing on upper North Street by the Pontoosuc Lake area.
-
Signal loop installation will occur on South Street.
Use caution when traveling on these roads. This schedule is subject to change based upon weather conditions.
|