Pittsfield Street Improvement Project: Nov. 10-14| 04:10PM / Saturday, November 08, 2025 | |
PITTSFIELD, Mass. Be advised that the following street improvements are scheduled from Nov. 10-14:
-
November 10 & 11: Milling and paving of Valentine Road from West Street to Taconic High School
-
Allengate Avenue driveway aprons will be installed during the week.
West Street project update
-
The construction of new sidewalks and curbing work continues. During this work, lane closures at various sections are expected. We encourage drivers to seek alternate routes if possible.
Sidewalk Repairs:
-
Wendell Avenue between Broad Street and Colt Road
-
Bartlett Avenue between East Housatonic Street and Colt Road
During this work, the sidewalks above will be closed for pedestrian use. Pedestrians are asked to use the sidewalks on the alternate side of the street while construction is underway. This work will take several weeks to complete and the weather may have an impact on the schedule.
Stormwater Improvements:
-
Glory Drive, contractor will be mobilizing equipment and materials to the area.
Additional utility work, in the right of way, will be occurring on the following streets:
-
King Street
-
Holmes Road
-
West Housatonic Street (Cadwell Road to Britton Street)
-
East Street (overhead utility work)
Please use caution when traveling on these roads. Drivers should seek alternate routes to avoid traffic delays. This schedule is subject to change based upon weather conditions.
|